Railway embankment rehabilitation using Mixed-in-Place method

For a green future

During a full closure of the railway line between Neukirchen and Vilseck, around 42,000 m² Mixed-in-Place panels were constructed as single panels – including roughly 2,700 single panels on three different railway embankments. To comply with the strict schedule and reopen the line for railway traffic as quickly as possible, six working crews carried out the drilling work, using two machines each in day and night shifts. A real feat of strength for the specialists from Bauer Spezialtiefbau. To further stabilize the embankment, roughly 50,000 m2 of geogrids were laid, along with the installation of 10,000 t of bentonite and 180 t of flow agent. What makes this project unique: This project was the first time the MIP method was used on a railway embankment.

Facts about the project
Company :

BAUER Spezialtiefbau GmbH

Location :

Vilseck, Germany

Project name :

Vilseck railway embankment rehabilitation 

Period :

May 2019 to July 2019

Services :

Soil improvement, railway embankment rehabilitation, Mixed-in-Place panels, drilling, stabilization work

A green heart: railway embankment rehabilitation in Vilseck

Für eine grüne Zukunft: Die Bahndammsanierung Vilseck mittels Mixed-in-Place-Verfahren
For a green future: Railway embankment rehabilitation in Vilseck using Mixed-in-Place method
Für den vierspurigen Ausbau der Autobahn A26 ist Bauer Spezialtiefbau mit umfangreichen Arbeiten beteiligt – und das bei besonders schwierigen Bodenverhältnissen.
Bauer Spezialtiefbau uses sustainable Mixed-in-Place ground improvement method for railway embankment rehabilitation in Vilseck.
Das Projekt Bahndammsanierung Vilseck von Bauer Spezialtiefbau
Das Projekt Bahndammsanierung Vilseck von Bauer Spezialtiefbau